RACP Selection Criteria

PDF version of this information in matrix format​                                                                                                                                ​          
The following selection criteria will be utilized in evaluating RACP Business Plans.  

​I. Job Creation/Retention (Tab 3) Maximum 40 Points
  • The maximum points can be obtained when the project produces 351 or more permanent direct new jobs with a median wage base that is at least a multiple of 2.51 of the county per capita income; retains at least 351 permanent direct jobs; produces at least 351 indirect jobs; and produces at least 101 construction jobs.
A. Permanent Direct New Jobs, created or vacant jobs being filled (includes filled positions transferred from out of state).
No. of New Jobs​ ​Points Scored
​0 0​​
1 to 27 1​
​​28 to 54 ​2
55 to 81 ​3
82 to 108 4​
109 to 135 5​
136 to 162 6​
163 to 188 ​7
189 to 215 8​​
216 to 242 9
243 to 269 ​10
270 to 296 ​11
297 to 323 ​12
324 to 350 ​13
351 or more ​14

B. Permanent Direct Retention Jobs
, filled positions that would be eliminated without the project (includes existing jobs currently located elsewhere in PA that will be relocated to this project).
​No. of Retained Jobs​ Points Scored​
0​ ​0
1 to 44 ​1
45 to 88 ​2
89 to 131 3​
132 to 175 4​
176 to 219 ​5
220 to 263 ​6
264 to 306 7​
307 to 350 8​
351 or more ​9
 
C. Permanent Indirect Jobs
No. of Indirect Jobs​​ ​Points Scored
0​​ 0​​
1 to 88 1​
89 to 175 ​2
176 to 263 ​3
264 to 350 4​
351 or more 5​
 
D. Construction Jobs, to complete project  
​​No. of Construction Jobs​ ​Points Scored​
1 to 50 1​
51 to 100 ​2
101 or more ​3
 
E. Wage Base of Jobs, fraction / multiples of per capita income of project location county
Fraction / Multiples of Per Capita Income of Project Location County​ ​Points Scored​
​0 ​0
.01 to .31 times​ ​1
.32 to .63 times​ ​2
​.64 to .94 times ​3
.95 to 1.25 times​ 4​
​1.26 to 1.56 times 5​
​1.57 to 1.88 times ​6
​1.89 to 2.19 times ​7
​2.20 to 2.50 times ​8
2.51 or more​ ​9
 
 
II. Community Impact (Tab 4) Maximum 20 Points
  • The maximum points can be obtained when the project: A.) is situated in a blighted, brownfield or related area; B.) improves the economic health of community; C.) enhances the quality of life; and D.) has a significant regional impact.
 
A. Redevelopment of Blight/Brownfield/Reclamation by project ​5 Points
 

B. Economic Health of Community​

  • Based on 1.) project located in county with unemployment higher than state average, 2.) declining population of county, 3.) county below state per capita income, or 4.) project located in KOZ/KOEZ/KIZ/KOIZ.
​5 Points
 

​C. Quality of Life

  • Based on 1.) project will create or improve Civic, Cultural or Recreation facility, 2.) improve commercial/retail/mixed-use building in downtown/core area, 3.) addresses immediate/urgent-improve quality of life, or 4.) addresses issues that could have negative impact-quality of life.
​​5 Points
 

D. Regional Impact​

  • Based on 1.) project consistent w/existing revitalization plan, 2.) joint effort of multiple municipalities, 3.) extent public engaged in development of project, or 4.) promote tourism.
​​​5 Points
 
 
III. Strategic Clusters for Development​ (Tab 5) Maximum 5 Points
  • The maximum points can be obtained when the project falls into two or more of the six targeted sectors.  The sectors are as follows: A.) Biotech/Pharmaceutical/Life Sciences; B.) High Tech & Advanced Manufacturing Materials; C.) Energy Extraction & Mining; D.) Business & Financial and Services; E.) Healthcare/Medical Research and/or Educational;  and F.) Agriculature.
No. of Cluster Categories Qualified for​ ​​Points Scored​
​0 0​
​1 ​3
​2 or more ​5

 

IV. Financial Impact Maximum
25 Points
  • The maximum points can be obtained when:
    1. the project has demonstrated its long term viability;
    2. the RACP grant is appreciably leveraged by a factor of five (5);
    3. the tax base has been increased by at least $2,000,000; and
    4. 50% or more of the project funding match is secured, and If project match includes any loans, the loans are all:
      • long-term (i.e., terms of 20 years or greater),
      • fully amortized, and
      • fully secured. 

​Project Viability

  • Based on review/analysis of business plan for sustainability, review/analysis of 3 years audited financial statements, and review/analysis of cash flow schedule.
​5 Points
 

​Dollars Leveraged, non-public funds

  • Note: For scoring purposes, OB intends to truncate the dollars leveraged factor to get a whole number.
​​Maximum 5 Points
 
Ratio of Non-Public Funds to RACP Funding in Project Points Scored​
​1 to 1 ​1
​2 to 1 ​2
​3 to 1 ​3
​4 to 1 ​4
​5 or greater to 1 ​5
  
​Increase to Tax Base (rounded to nearest thousand) Maximum 10 Points​
 
Tax Base Increase​ ​Points Scored​
​$0 ​0
​$1 to $220K ​1
​$221K to $440K ​2
​$441K to $660K ​3
​$661K to $890K ​4
​$891K to $1.11M ​5
​$1.111M to $1.33M ​6
​$1.331M to $1.55M ​7
​$1.551M to $1.77M ​8
​$1.771M to $1.99M ​9
​$2M or more ​10
 

Project Match

  • Both of the items below must apply:
    • At least 50% of total project match funding is secured (only land that was acquired within 1 year prior to business plan submission, or is a prospective acquisition, is considered “secured” for purposes of this calculation)
    • All match loans are 100% secured, long-term, and fully amortized
​​5 Points
 
 
V. Shovel Readiness Maximum
10 Points
  • The maximum points can be obtained when the anticipated construction start date is scheduled to occur within 180 days of the submission date of the Business Plan. 
​Project Construction will start within this many days of the BP submission deadline for the Round ​Points Scored​
​0 (i.e.,already started) to 180 ​10
​181 to 365 ​5
​366 or more

​0

(& project is not eligible for this Round)

 
 
Scoring Matrix.pdfScoring Matrix.pdf